On Wednesday the 02nd of September 2015, Ofcom engineers visited our site to complete the required commissioning tests.  With these tests passed, we began initial test transmissions later that day.  Test transmissions were completed on Sunday the 13th of September 2015 with the multiplex transmission licence taking effect at midnight / 00:01 on Monday the 14th of September.

We originally expected our trial broadcasts to operate for an initial period of nine months, into mid-June 2016. On Wednesday the 24th of February 2016, it was announced by Ofcom that our trial licence would be extended for a further two years, allowing us to continue our initial operations until mid June 2018. More recently, early in 2018 our trail licence was extended again, this time until early 2020. However, we had hoped to be able to apply for and secure a permanent licence at some point during mid to