Description: This project is almost complete! Stay tuned! Construction in progress - October 2023 Project during initial phases of construction (underground work) Project No.: 40-B30637 & 40-B30833 LocationsSW/SE 9 Street from SW 1 Avenue to South Miami AvenueSW/SE 10 Street from SW 1...
COVID-19 General Information and ARPA Relief Funds
SW 7 th Street to SW 8 th Street – milling, resurfacing and temporary striping work is complete on this segment!
SW 9 th Street to SW 11 th Street – manholes adjusting and leveling work on these three streets (SW 9 th , 10 th and 11 th Streets on SW 1 st Avenue)